Checks before mounting

  1. Perform the following checks: D = detailed check, N = close inspection, S = visual inspection

Test schedule

D

N

S

I

Unit corresponds to EPL/zone requirements of the installation location.

II

Correct device group.

 

III

Correct temperature class for units.

 

IV

Degree of protection (IP degree) of units corresponds to level of protection / group / conductivity.

V

Unit power circuit name present and correct.

VI

Housing and connections satisfactory.

VII

Before installing, check that the motor bearing is functioning properly.

The impeller is balanced in accordance with ISO 14694 and ISO 1940-1. The vibration level of units is checked ex factory in accordance with ISO 14694. The vibration level must be checked again at the installation site in accordance with ISO 14694 (vibration values according to category and prescribed limit values).