Checks before mounting
- Perform the following checks: D = detailed check, N = close inspection, S = visual inspection
Test schedule | D | N | S | |
---|---|---|---|---|
I | Unit corresponds to EPL/zone requirements of the installation location. | ● | ● | ● |
II | Correct device group. | ● | ● |
|
III | Correct temperature class for units. | ● | ● |
|
IV | Degree of protection (IP degree) of units corresponds to level of protection / group / conductivity. | ● | ● | ● |
V | Unit power circuit name present and correct. | ● | ● | ● |
VI | Housing and connections satisfactory. | ● | ● | ● |
VII | Before installing, check that the motor bearing is working properly. | ● | ● | ● |