Preparations for ER-APB wall installation (with fire protection)
12 | Main duct (steel folded spiral-seams duct) |
13 | Spigot |
14 | Shaft wall |
15 | Ceiling compound |
16 | Floor ceiling |
17 | Connection duct: Flexible aluminium duct AFR 80 |
18 | Sealing material, e.g. cold-shrink tape |
Requirements in line with approval).
(- Correctly attach main ventilation duct inside the shaft.
- Apply ceiling compound. To do this, encase the ceiling and pour in the material from above.
- Make a wall or shaft opening for the flexible aluminium duct.
Danger to life due to fire transmission in case of faulty ceiling compound.
- It is essential that the remaining gap between the main duct and the wall or ceiling is completely sealed with non-flammable materials that are resistant to deformation. For example, use concrete or cement mortar.
- Connect the flexible aluminium duct to the main duct and seal for ventilation.
- Cut flexible aluminium duct to length, observe a maximum duct length of 2 m.
- Ensure a suitable, level substructure.
- Attach spigot made from shaft material F90 around the shaft.
- Continue with the safety test of the APB shut-off device: Electrically connecting the unit.