Checks before mounting
- Perform the following checks: D = detailed check, N = close inspection, S = visual inspection
Test schedule | D | N | S | |
---|---|---|---|---|
I | Unit corresponds to EPL/zone requirements of the installation location. | ● | ● | ● |
II | Correct device group. | ● | ● |
|
III | Correct temperature class for units. | ● | ● |
|
IV | Degree of protection (IP degree) of units corresponds to level of protection / group / conductivity. | ● | ● | ● |
V | Unit power circuit name present and correct. | ● | ● | ● |
VI | Housing and connections satisfactory. | ● | ● | ● |
VII | Before installing, check that the motor bearing is functioning properly. | ● | ● | ● |
- Before installation, check the application category of the units and the vibration limits for on-site tests, in particular for the start-up, alarm and stop operating statuses. Run a vibration check and check the vibration values after commissioning (ISO 14694, BV-3, Veff. max. 4.5 mm/sec.). If required, install components for avoiding vibration.
- Install the command equipment needed for starting, stopping, emergency stops or resetting after an emergency stop. Undertake installations in accordance with the planning documents and relevant regulations (EN 60079-14).
- Install a function monitor with alarm function to warn persons in case of malfunctions/unit failure and to avoid damage to property.